According to the recent Citizen Survey, the biggest area of concern to residents was maintenance.

  • 53% felt city should spend more on maintenance of streets & sidewalks
  • Citizens were unhappy with the current condition of streets & sidewalks
  • Residents felt the city was taking too long to repair streets

        
Street improvement projects

Over half of the $41 million dedicated to the 5-year improvement plan will be spent on improving city streets.

Learn more and see how your street compares!

5-Year Construction & Maintenance Plan Projects
Following is a list of projects included in the 5-year maintenance & construction plan. The schedule may change as projects are coordinated with other agencies, such as the Cape Fear Public Utility Authority and the North Carolina Department of Transportation in an effort avoid duplication and unnecessary cost.

Download a printable, more detailed version of the plan schedule.









 




        Project         5-Year Total
        Streets, Sidewalks & Transportation        
        Streets rehabilitation       21,000,000
        Multimodal Transportation Center        600,000
        Kerr Ave. bicycle facility (w/sidewalks)       1,140,000
        N. 3rd St. Bridge project        350,000
        Sign inventory & assessment       90,000
        North/South 17th Street       250,000
        Sidewalk rehab/repairs       750,000
        Pedestrian/bike improvements       1,350,000
        Bridge repair       886,300
        Cinema Drive        600,000
        Coordinated improvements w/CFPUA        2,858,250
        Wayfinding signage        72,000
        Front & Red Cross signal       406,000
        Total        30,352,550
                 
        Riverwalk & Riverfront Improvements      
        Conlon Pier repair       1,712,000
        Coastline Inn bulkhead stabilization       1,012,184
        Market St. H piles stabilization       359,100
        Riverwalk pocket parks stabilization       466,000
        Water St. shoreline stabilization       216,000
        Dram Tree shoreline stabilization       387,000
        Church St. shoreline stabilization       193,500
        Riverwalk Brooks Building       280,800
        Market St. bulkhead repair       200,600
        Total        4,827,184
                 
        Parks Improvements        
        Park facilities maintenance       1,000,000
        Alderman Preserve - Phase I       1,325,000
        Riverfront Park rehabilitation       250,000
        Empie Park improvements       1,439,570
        Olsen Park - Phase II       180,000
        Total       4,194,570
                 
        Public Facilities        
        Building maintenance       1,644,500
        Total       1,644,500
Layout - Right Frame
Layout - Footer Top Left Corner Layout - Footer Top Right Corner
Terms of Use  Privacy  ADA Policy  ©2002-2014 City of Wilmington 
102 North Third Street - Post Office Box 1810
Wilmington, North Carolina 28402-1810
910.341.7800
Questions, Comments? Email Us!
Login