Update for Shipyard Boulevard Fire Station #5

Concrete Pour

Post Date:12/04/2017 7:58 AM
Station 5 Concrete PourConstruction began in July and as of late November, site and building pad preparation, foundation construction and below slab utility installation have been completed.  Last week, the contractor completed the administration/living area floor slab preparation and concrete is expected to be poured in the next couple of days.  Vertical building construction began in November and apparatus bay walls are well underway.  The construction contract duration is approximately twelve (12) months with a scheduled opening in July 2018. 