Statuses of major Hurricane Florence Repairs

Post Date:12/18/2019 3:53 PM

 

ilmstrong, bridge, aerial, evening

 

 

 

 

The City of Wilmington incurred millions of dollars worth of damage from the catastrophic Hurricane Florence, which made landfall in the City in September 2018. Since then, the City has been working diligently to repair that damage. 

After addressing immediate repairs following the storm, staff worked for several months to identify all the city streets, sidewalks, buildings and drainage infrastructure across the city that need to be repaired. The city also had to get federal officials to inspect and approve each of the repair sites to make sure the city could receive federal/state reimbursement before the projects could go forward.

Because the city has to pay for all of these repairs out-of-pocket with taxpayer dollars, the federal inspections and approval were critical to make sure the city gets reimbursed for as much as possible. So far, the city has spent or appropriated more than $34 million in response to the storm and hopes to get much of that reimbursed. You can also track the projects here. 

Here's the status of each project:

Garden Avenue – Ongoing 

Repairs to Garden Avenue began the week of Dec. 30. The scope of work on this project involves in-situ rehabilitation of a 54-inch corrugated metal pipe. The work consists of sealing pipe joints and penetrations, pipe back-grouting and probe grouting for soil stabilization using moisture-activated hydrophilic and/or hydrophobic polyurethane resins. It will also include centrifugal spin casting and lining of the storm drain lines and structures and the  removal and replacement of existing storm structures, and certain portions of the 54” pipe. The $456,962.16 contract is expected to take 90 days. Contractor Applied Polymerics of Mt. Airy NC uses existing manholes to access the pipes, and inject foam-like material that fills the pipes’ cracks from within and then hardens. Garden Avenue will be close to through traffic, but a detour will be open at Cherry Avenue. 

 

 

Crews perform hurricane repairs on Shirley St
70 Point Repair Project – Ongoing 

Crews began work on Shirley Road Monday, Dec. 16 to repair cave-ins resulting from Hurricane Florence as part of a large storm water infrastructure project. Shirley Road is the first of 70 sites to be repaired throughout the city. FEMA will reimburse the City for the $2.4 million project, which is expected to be completed within 6 months. Carolina Civil Works is performing the repairs.

 

 

 

 Crews perform hurricane repairs on River RoadRiver Road – Ongoing 

A six-month closure of River Road began in September so crews can replace a large drainage culvert beneath River Road. The culvert, located just south of Raleigh Street, was originally damaged in 2017 and failed again during Hurricane Florence. Temporary repairs and paving have allowed the road to remain open in the meantime while planning for this replacement. The Cape Fear Public Utility Authority is contributing $885,000 of the total project cost of $1.37 million because it involves the relocation of a force main sewer line.Trader Construction of New Bern is performing the work.

 

 

Crews perform hurricane repairs on sidewalksSidewalk Repairs – Ongoing 

Crews are nearly finished with on repairs to approximately 50 sidewalks damaged by Hurricane Florence. In-house crews are doing some of the work while a contractor is working on the larger sidewalk repair projects. Repairs made by city crews so far include South 14th Street, McClelland Drive, Winston Boulevard, 43rd Street and Country Club Road, as well as sidewalks in the Glen Meade/South Oleander and Audubon/Devon Park neighborhoods.

 

 

Crews perform hurricane repairs on Henry StHenry Street, Caswell Street Repairs – Finished 

As part of a second phase of major Hurricane Florence repairs to city infrastructure now underway, crews finished repairs to drainage pipes beneath Henry Street and Caswell Street in September.The $529,000 project involves a repair method that prevents the need to dig up or close the street. Contractor Applied Polymerics of Mt. Airy NC uses existing manholes to access the pipes, and inject foam-like material that fills the pipes’ cracks from within and then hardens. The crews also removed sand that has gotten into the pipes as a result of the cracks. 

 

 

Crews perform hurricane repairs on Montgomery Ave

Montgomery Avenue, Shell Road Village Drive Repairs – Finished 

Crews finished hurricane repairs to Montgomery Avenue and Shell Road Village Drive in December. The project is part of a $431,296 contract that  involves fixing underground drainage pipes using a method that prevents the need to dig up the street. Contractor Vortex Services of Florida uses existing manholes to access the pipes and inject a liner that fills the pipes’ cracks and holes from within and then hardens into a new pipe. 

 

 

 Sidewalk Repairs –Ongoing

City of Wilmington crews are nearly finished with repairs to approximately 50 sidewalks damaged by Hurricane Florence. In-house crews are doing some of the work while a contractor is working on the larger sidewalk repair projects.

 Sidewalk Repairs –Ongoing

City of Wilmington crews are nearly finished with repairs to approximately 50 sidewalks damaged by Hurricane Florence. In-house crews are doing some of the work while a contractor is working on the larger sidewalk repair projects.

 Sidewalk Repairs –Ongoing

City of Wilmington crews are nearly finished with repairs to approximately 50 sidewalks damaged by Hurricane Florence. In-house crews are doing some of the work while a contractor is working on the larger sidewalk repair projects.

 Sidewalk Repairs –Ongoing

City of Wilmington crews are nearly finished with repairs to approximately 50 sidewalks damaged by Hurricane Florence. In-house crews are doing some of the work while a contractor is working on the larger sidewalk repair projects.