Both proposed alternatives would add something the existing bridge lacks: a multi-use path across the Cape Fear River.
But connectivity doesn't end at the bridge.
On the Brunswick County side, the proposed path does not connect to an existing bicycle or pedestrian network.
On the Wilmington side, NCDOT's analysis also assumes a four-lane configuration on 5th Avenue. This configuration was replaced by the City’s investment in new bicycle infrastructure.
For people living near the project, the changes would also be heard. NCDOT identified potential traffic noise impacts under both alternatives, with more locations potentially affected under Alternative B.
Before you go, think about: A new multi-use path could create a connection across the river, but what happens when you get to the other side? How should the project connect with existing streets, bike infrastructure, neighborhoods, and the people who live along them?
Source: NCDOT Environmental Assessment, Sections 2.4, p. 6; 3.2.4, pp. 24-27; and 3.2.6, p. 29; Appendix D: Community Characteristics Report, p. 269.